Parliamentary Papers, Nide 12H.M. Stationery Office, 1959 |
Kirjan sisältä
Tulokset 1 - 3 kokonaismäärästä 83
Sivu 12
... change from direct current to alternating current . One consent was for a change from 230/400 volts to 11,000 volts and one was for 230/400 volts to 6,600 volts . The remaining three consents were for changes from 10,500 volts to 11,000 ...
... change from direct current to alternating current . One consent was for a change from 230/400 volts to 11,000 volts and one was for 230/400 volts to 6,600 volts . The remaining three consents were for changes from 10,500 volts to 11,000 ...
Sivu 48
... changes in their Bulk Supply Tariff to operate from 1st April , 1959 , and consequently the Area Board found it desirable to recast their present Maximum Demand Tariffs in a similar manner , i.e. , an increase in the kilowatt charge but ...
... changes in their Bulk Supply Tariff to operate from 1st April , 1959 , and consequently the Area Board found it desirable to recast their present Maximum Demand Tariffs in a similar manner , i.e. , an increase in the kilowatt charge but ...
Sivu 3
... Changes 12. In last year's Report , the Board spoke of changes in the structure of the Farm Tariff designed to ensure that farmers making little use of electricity pay a fair contribution towards the fixed costs of maintaining the ...
... Changes 12. In last year's Report , the Board spoke of changes in the structure of the Farm Tariff designed to ensure that farmers making little use of electricity pay a fair contribution towards the fixed costs of maintaining the ...
Sisältö
Electricity Supply Industry in England and Walesmaps | 1 |
CONSUMER SERVICE SALES AND LOAD FACTOR | 15 |
Relations with Other Bodies | 25 |
Tekijänoikeudet | |
178 muita osia ei näytetty
Muita painoksia - Näytä kaikki
Yleiset termit ja lausekkeet
1st April 1st January 31st December Alderman allocated amount Appendix Area Boards Balance Sheet British Electricity Stock Bulk Supply Tariff capacity capital expenditure cent Central Electricity Central Electricity Authority Central Guarantee Fund charges Committee contributions Councillor Deputy Chairman District East Midlands Electricity Act Electricity Consultative Council Electricity Council Electricity Generating Board electricity supply employees ended 31st March England and Wales fifteen months ended financing expenses Fixed Assets Grid hire purchase increase installed kilowatts load factor LONDON ELECTRICITY BOARD main transmission maximum demand Merseyside MIDLANDS ELECTRICITY BOARD million Minister of Power Miscellaneous months ended 31st North Eastern Notes on Accounts operation organisation overhead lines paragraph payment period plant power stations premises programme provision respect Revenue Account Road sales of electricity Sales of Fittings schemes Section staff Sub-Area substation sumers Superannuation surplus Tariff Total Total stations transferred transformer tricity unit sold units per quarter voltage volts